Abel - Ball (formerly Abel-Moody) |
Project Purpose:To meet increased electricity demand and growth in the Queen Creek, Arizona area. Project Type: New Estimated In-Service Date: 4/15/2019 Estimated Transfer Capability/Rating (MW): 875 Sponsoring Organization(s):Salt River Project Voltage Class: 200-300kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
Ault-Cherokee |
Project Purpose:This proposed project will allow approximately 300-600 megawatts of additional generation from Energy Resource Zone 1, interconnected at or near the Ault Substation. The proposed project consists of approximately 90 miles of new transmission, starting at Public Service Company of Colorado’s (PSCo) Ault Substation and ending at its Cherokee Station in Denver. A single 59-mile line will be built from Ault Substation to a location near the PSCo Ft. Lupton Substation. From this point, the existing 115-kV line from Ft. Lupton to Cherokee Station will be rebuilt so that one circuit continues to operate at 115-kV and serve Tri-State Generation and Transmission Association (Tri-State) load; the other circuit will operate as a 26-mile double circuit, 230-kV line, completing the circuit from Ault to Cherokee Station. Project Type: New Estimated In-Service Date: 12/31/2016 Estimated Transfer Capability/Rating (MW): 600 Sponsoring Organization(s):Public Service of Colorado (PSCo) Voltage Class: 300-450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CCPG
|
Bighorn-Eldorado |
Project Purpose:Move Solar Renewable Energy from the Jean and Pahrump Nevada area to Eldorado Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):NV Energy Voltage Class: >450kV DC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SWAT
|
Boardman-Hemingway 500 kV (B2H) |
Project Purpose:The B2H project will increase transmission capacity between the Pacific Northwest and Idaho to provide: dependable electrical service for Idaho Power network load, access to energy markets, and transmission service to eligible customers. Project Type: New Estimated In-Service Date: 6/1/2016 Estimated Transfer Capability/Rating (MW): 1,300 Sponsoring Organization(s):Idaho Power Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: NTTG
|
Canada – Northern California Transmission Project – Avista Corporation 500/230 kV AC Interconnection |
Project Purpose:TBD Project Type: New Estimated In-Service Date: 1/1/2015 Estimated Transfer Capability/Rating (MW): 500 Sponsoring Organization(s):Avista Corporation Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group:
|
Canada/Pacific Northwest-Northern California |
Project Purpose:To enable delivery of renewable energy and conventional energy from BC and PNW to destination markets in California, and also to reduce congestion not only on the COI/PDCI paths but also reduces path utilization WECC-wide. Project Type: New Estimated In-Service Date: 1/1/2021 Estimated Transfer Capability/Rating (MW): 3,000 Sponsoring Organization(s):BC Hydro Voltage Class: >450kV AC, >450kV DC WECC Project Rating Review Status: Phase 2 Subregional Planning Group:
|
Cascade Crossing |
Project Purpose:Satisfies Generation Interconnection Requests. Supports compliance with state Renewable Energy Standard. Project Type: New Estimated In-Service Date: 12/1/2016 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):Portland General Electric
Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: CG, NTTG
|
Cedar Mountain Loop-in of Moenkopi-Yavapai 500kV Line |
Project Purpose:This project is needed for the interconnection of a large wind generation project, which is listed in the APS Generator Interconnection Queue as project #113. The switchyard ownership is expected to be the same as the 500kV line. Project Type: New Estimated In-Service Date: 12/31/2011 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group:
|
Centennial West Clean Line |
Project Purpose:To connect exceptional renewable energy resources to population centers. Project Type: New Estimated In-Service Date: 1/1/2018 Estimated Transfer Capability/Rating (MW): 3,500 Sponsoring Organization(s):Clean Line Energy Partners LLC Voltage Class: >450kV DC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: CTPG, SWAT, CAISO
|
Central Ferry - Lower Monumental (Little Goose Area Reinforcement) |
Project Purpose:The proposed line is needed to increase the electrical capacity of BPA's transmission system in response to requests for transmission service in this area, primarily related to planned wind generation facilities. Project Type: New Estimated In-Service Date: 7/31/2013 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):BPA Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CG
|
Chinook |
Project Purpose:Facilitate movement of energy between Montana, Idaho and the Southwest US Project Type: New Estimated In-Service Date: 12/31/2018 Estimated Transfer Capability/Rating (MW): 3,000 Sponsoring Organization(s):TransCanada Voltage Class: >450kV DC WECC Project Rating Review Status: Phase 1 Subregional Planning Group:
|
Delaney-Palo Verde 500kV Line |
Project Purpose:This project is initially needed to interconnect multiple solar generation projects at the Delaney switchyard. This line is also one section of a new 500kV path from Palo Verde around the western and northern edges of the Phoenix area and terminating at Pinnacle Peak. This is anticipated to be a joint participation project. APS will serve as the project manager. Project Type: New Estimated In-Service Date: 12/1/2013 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SWAT
|
Delany-Sun Valley 500kV Line |
Project Purpose:This project will serve projected need for electric energy in the area immediately north and west of the Phoenix Metropolitan area. It will increase the import capability to the Phoenix Metropolitan area. It will increase the import capability to the Phoenix Metropolitan area as well as increase the export/scheduling capability from the Palo Verde area to provide access to both solar and gas resources. The project will also increase the system reliability by providing a new transmission source to help serve the areas in the western portions of the Phoenix Metropolitan area. This is a joint participation project with APS as the project manager. Project Type: New Estimated In-Service Date: 5/1/2015 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
Desert Basin - Pinal Central |
Project Purpose:Improve the reliability of the Desert Basin Generating Station, to allow the plant to operate at full output without limitations and increase the capacity of the local transmission system. Project Type: New Estimated In-Service Date: 4/15/2014 Estimated Transfer Capability/Rating (MW): 630 Sponsoring Organization(s):Salt River Project Voltage Class: 200-300kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
Devers - Colorado River 500 kV (DCR) Transmission Line Project |
Project Purpose:The purpose of this project is to interconnect renewables from Colorado River 500 kV Substation. Project Type: New Estimated In-Service Date: 12/31/2013 Estimated Transfer Capability/Rating (MW): 1,200 Sponsoring Organization(s):SCE Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: CTPG, CAISO
|
ECO 500/230/138kV Substation |
Project Purpose:To accomodate new generation interconnections in the Eastern section of San Diego County and in Mexico. Also, to reduce operation, maintenance, and outage exposure issues with the existing 19 mile radial tap serving Crestwood and Boulevard substations. Project Type: New Estimated In-Service Date: 9/1/2012 Estimated Transfer Capability/Rating (MW): Sponsoring Organization(s):San Diego Gas & Electric Voltage Class: <200kV AC, 200-300kV AC, >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CAISO
|
Gateway Central Project – Mona to Oquirrh 500 kV (Energy Gateway Segment C) |
Project Purpose:Meet load growth, provide increased reliability and improved operational flexibility in conjunction with future generation resources, including renewable resources. Project Type: New Estimated In-Service Date: 6/1/2013 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):PacifiCorp Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: NTTG
|
Gateway Central Project, Sigurd - Red Butte 345 kV Line |
Project Purpose:Load service and increased reliability for SW Utah load service
Note: estimated transfer capability
550 MW (s-n)
400 MW (n-s) Project Type: New Estimated In-Service Date: 6/1/2014 Estimated Transfer Capability/Rating (MW): 600 Sponsoring Organization(s):PacifiCorp Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: NTTG
|
Gateway South Project – Segment #1 (Mona-Crystal 500 kV) |
Project Purpose:Increased capacity option for Third party usage Project Type: New Estimated In-Service Date: 12/31/2050 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):PacifiCorp Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: NTTG
|
Gateway South Project – Segment #2 (Aeolus-Mona 500 kV) |
Project Purpose:Delivery of network resources to network load. Load growth requirements. Project Type: Upgrade Estimated In-Service Date: 1/1/2019 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):PacifiCorp Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: NTTG
|
Gateway West Transmission Project Segment 1A – Windstar to Jim Bridger 230 kV, 500 kV |
Project Purpose:Delivery of new resources in transmission service request queues, to ensure reliable electric service to customers and to also accommodate regional needs for integrating renewable and other resource development. Note: two 230 kV lines from Windstar to Aeolus and a single 500 kV circuit 500 kV line from Aeolus to Bridger. Project Type: New Estimated In-Service Date: 6/1/2017 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s): PacifiCorp and Idaho Power Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 completed Subregional Planning Group: NTTG
|
Gateway West Transmission Project Segment 1B – Jim Bridger to Southeast Idaho (Bridger – Populus single circuit 500 kV) |
Project Purpose:Delivery of new resources in transmission service request queues, to ensure reliable electric service to customers and to also accommodate regional needs for integrating renewable and other resource development. Project Type: New Estimated In-Service Date: 1/1/2017 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):PacifiCorp and Idaho Power Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: NTTG
|
Gateway West Transmission Project Segment 1C – Southeast Idaho – South Central Idaho (Populus – Midpoint 500 kV) |
Project Purpose:Increased capacity to serve customer growth and reliably deliver energy to customers; support new renewable and other resource development Project Type: New Estimated In-Service Date: 1/1/2018 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):PacifiCorp and Idaho Power Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: NTTG
|
Gateway West Transmission Project Segment E – South to Southwest Idaho (Midpoint – Hemingway 500 kV) |
Project Purpose:Increased capacity to serve customers and reliably deliver energy to customers; support new renewable and other resource development. Project Type: New Estimated In-Service Date: 1/1/2018 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):PacifiCorp and Idaho Power Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: NTTG
|
Great Basin HVDC |
Project Purpose:The project is an underground HVDC cable which ties the Northern Nevada and Northern California markets together. It is in a common corridor with an interstate natural gas pipeline. GBHVDC facilitates transport of stranded renewable generation to more efficently reach loads in Northern CA. Additonally, the project provides reliability improvments in the Reno and Sacramento areas via its voltage source commutated HVDC conversion technology. Project Type: New Estimated In-Service Date: 12/31/2016 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Great Basin Energy Development, LLC (GBHVDC) Voltage Class: >450kV DC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: CTPG, SIERRA, CAISO
|
Harcuvar Transmission Project |
Project Purpose:To permit interconnection of potential solar and thermal generation to the grid with access to the Palo Verde hub, California ISO and WAPA’s Parker-Davis transmission system. Project Type: New Estimated In-Service Date: 1/1/2015 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):Central Arizona Water Conservation District Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
Hassayampa - North Gila 500kV #2 line |
Project Purpose:As a new transmission path to the Yuma area, this 500kV line will provide transmission capacity required to supplement limited transmission and generation resources in the Yuma area. Project Type: New Estimated In-Service Date: 5/1/2015 Estimated Transfer Capability/Rating (MW): 1,200 Sponsoring Organization(s):Arizona Public Service Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: CTPG, SWAT
|
Hassayampa-Pinal West #2 |
Project Purpose:Deliver generator resources at the Palo Verde hub (including Hassayampa) to Pinal and Maricopa counties in Arizona.
Project has a "TBD" in-service date. Project Type: New Estimated In-Service Date: 12/31/8900 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):Salt River Project Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
Hemingway-Captain Jack 500 kV Transmission Line |
Project Purpose:Increased system flexibility and reliability between PacifiCorp’s East and West Control Areas, relieve congested paths Idaho to Northwest and connect to resource centers in Wyoming to Southern Oregon loads; support new renewable energy development.. Project Type: New Estimated In-Service Date: 1/1/2030 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):PacifiCorp Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: NTTG
|
High Plains Express Transmission Project |
Project Purpose:Enhance reliability, access renewable energy resources, and allow the transfer of economical energy resources to customers in Wyoming, Colorado, New Mexico, and Arizona Project Type: New Estimated In-Service Date: 1/1/2017 Estimated Transfer Capability/Rating (MW): 4,000 Sponsoring Organization(s):Black Hills Corporation; Colorado Springs Utilities; Public Service Company of New Mexico, Public Service Company of Colorado (Xcel Energy); Salt River Project; Tri-state Generation &Transmission; Trans-Elect Development Company; Western Area Power Administration; Colorado Clean Energy Development Authority; New Mexico Renewable Energy Transmission Authority; and Wyoming Infrastructure Authority Voltage Class: 300-450kV AC, >450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: CCPG, SWAT
|
Hoodoo Wash Loop-in of Hassayampa-North Gila 500kV #1 Line |
Project Purpose:This project is needed for the interconnection of the Agua Caliente Solar Project, which is a 500MW solar project. The switchyard is also the location of numerous other generator interconnection requests within APS’s Generator Interconnection Queue. Project Type: New Estimated In-Service Date: 12/31/2011 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CTPG, SWAT
|
I-5 Corridor Reinforcement Project (Castle Rock - Troutdale) |
Project Purpose:Primarily to serve the growth in southwest Washington and northwest Oregon load. Also Capacity Increase and Congestion Relief to serve Point-to-Point Transmission Service Requests which impact the South of Allston path. Project Type: New Estimated In-Service Date: 12/1/2015 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Bonneville Power Administration (BPA) Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: CG
|
Interior to Lower Mainland Transmission (ILM) Project |
Project Purpose:The transmission circuits that bring power from generation resources in the north and southern Interior of the province of British Columbia to the Lower Mainland and Vancouver Island are some of the most critical paths in the transmission grid. Built in the early 1970s, the circuits are reaching the limits of their capacity during periods of peak demand. The ILM Project will expand the capacity of these essential transmission circuits so that they can continue to reliably deliver clean renewable energy to the Lower Mainland and Vancouver Island. Project Type: New Estimated In-Service Date: 10/31/2014 Estimated Transfer Capability/Rating (MW): 6,550 Sponsoring Organization(s):BC Hydro Voltage Class: >450kV DC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: BCCPG
|
Juan de Fuca HVDC Sea Cable |
Project Purpose:Improved system reliability and increase in flow from mainland to meet needs of Vancouver Island residents. Project Type: New Estimated In-Service Date: 1/1/2013 Estimated Transfer Capability/Rating (MW): 550 Sponsoring Organization(s):Sea Breeze Pacific Juan de Fuca Cable, LP Voltage Class: WECC Project Rating Review Status: Phase 2 Subregional Planning Group:
|
Juan de Fuca II HVDC Cable |
Project Purpose:No Information Available Project Type: New Estimated In-Service Date: 1/1/2015 Estimated Transfer Capability/Rating (MW): 1,100 Sponsoring Organization(s):Sea Breeze Pacific Regional Transmission System, Inc (SBP-RTS) Voltage Class: WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
Lake Elsinore Advanced Pumped Storage (LEAPS Transmission Project (Talega-Escondido / Valley-Serrano 500 kV line) |
Project Purpose:Delivery of LEAPS generation to the regional network. Project Type: New Estimated In-Service Date: 1/1/2009 Estimated Transfer Capability/Rating (MW): 500 Sponsoring Organization(s):Nevada Hydro Company, Inc. and The Lake Elsinore Valley Municipal Water District Voltage Class: <200kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group:
|
Lamar-Front Range |
Project Purpose:Lamar-Front Range 345 kV Transmission ProjectQuick FactsEstimated cost: $294 millionProposed in-service date: 2016-2017Maps: Project MapFactsheet: Project SummaryThis proposed project consists of approximately 350 miles of high voltage transmission and has two major components: a Lamar-Comanche 345-kV line and a Lamar-Missile Site 345-kV line.
The proposed project will allow approximately 800-1,000 megawatts of additional generation in Energy Resources Zone 3, interconnected at or near Public Service Company of Colorado’s (PSCo) Lamar Substation. Studies indicate that the area is transmission-deficient and requires a robust backbone network to deliver potential and anticipated generation to load centers in Colorado.
Based on studies and discussions with the Colorado Coordinated Planning Group (CCPG), a joint, high voltage transmission system planning forum, the proposed project is the preferred first phase project to accommodate resources in Energy Resource Zone 3. PSCo and Tri-State Generation and Transmission Association (Tri-State) are actively performing joint technical studies for a coordinated joint participation project, including the execution of a letter agreement describing participation in the proposed project. Project Type: New Estimated In-Service Date: 12/31/2017 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Public Service of Colorado (PSCo) & Tri-State G&T Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: CCPG
|
Lamar-Vilas |
Project Purpose:This proposed project consists of approximately 57 miles of transmission from Public Service Company of Colorado’s (PSCo) Lamar Substation to a new substation near the town of Vilas, Colorado. The proposed project was identified in 2007 as a way to accommodate generation resources in Baca County. However, system studies indicate that any additional generation at Lamar will require significant upgrades, such as the proposed Lamar-Front Range transmission line. This proposed project could not accommodate any new generation unless the Lamar-Front Range transmission line is also in place. Project Type: New Estimated In-Service Date: 12/31/2017 Estimated Transfer Capability/Rating (MW): 680 Sponsoring Organization(s):Public Service of Colorado (PSCo) Voltage Class: 200-300kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CCPG
|
Las Vegas - Los Angeles Transmission Project |
Project Purpose:Increase the transfer capability from the Eldorado valley area to southern California, WECC Path 46 Project Type: New Estimated In-Service Date: 5/1/2017 Estimated Transfer Capability/Rating (MW): 3,000 Sponsoring Organization(s):Energy Capital Partners
PDS Consulting Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CTPG, SWAT
|
Lassen Double-Circuit 230kV line |
Project Purpose:The project presents the opportunity to expand the Western Interconnection transmission capabilities in a substantial fashion. The new path would allow for the delivery of well documented renewable supplies in Northern Nevada and Northeastern California to load centers in California and assist in meeting California's RPS goals. Project Type: New Estimated In-Service Date: 6/1/2016 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Lassen Municipal Utility District Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SIERRA
|
Lucky Corridor Transmission Project |
Project Purpose:Transport electricity from renewable energy and natural gas in Northern New Mexico to Four Corners for sale to western markets Project Type: Upgrade Estimated In-Service Date: 4/1/2015 Estimated Transfer Capability/Rating (MW): 900 Sponsoring Organization(s):Lucky Corridor, LLC Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SWAT, None
|
Midway-Waterton |
Project Purpose:This project consists of approximately 82 miles of 345 kV transmission between the Midway Substation and the Waterton Substation, south of the Denver metro area.
Seventy-three miles of existing line will be reenergized at 345 kV, while nine miles will be rebuilt to 345 kV. The project includes 345 kV switchyard additions at Midway and Waterton substations. It also includes other changes at Waterton: replacement of two 230/115 kV autotransformers; expansion and capacity upgrades to the 230 kV switchyard; and capacity upgrades to the 115 kV switchyard.
The project will allow 300-500 megawatts of additional generation. The project also will facilitate potential generation resources in Energy Resource Zones 3, 4 and 5, while improving system reliability. The project received a Certificate of Public Convenience and Necessity (CPCN) in May 2009. The project is in progress Project Type: New Estimated In-Service Date: 6/30/2011 Estimated Transfer Capability/Rating (MW): 1,200 Sponsoring Organization(s):Public Service of Colorado Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: CCPG
|
Montana Alberta Tie-Line |
Project Purpose:Enable direct movement of energy between Alberta and Montana Project Type: New Estimated In-Service Date: 6/30/2012 Estimated Transfer Capability/Rating (MW): 300 Sponsoring Organization(s):Montana Alberta Tie Ltd. (MATL) Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group:
|
Morgan-Sun Valley 500kV Line |
Project Purpose:Increases import capability for the Phoenix Metropolitan area and export/scheduling capability from the PV area which includes both solar and gas resources. Increases transmission system reliability and ability to deliver power from these resources. Provides a second 500kV source for the Sun Valley substation. Provides support for multiple Category C and D transmission contingencies. Project Type: New Estimated In-Service Date: 6/1/2016 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
Mountain States Transmission Intertie (MSTI) (Townsend-Midpoint 500 kV) |
Project Purpose:Provide capacity to relieve congestion from Montana to Idaho and to meet requests for transmission service to move renewable power from Montana to load centers outside Montana. Project Type: New Estimated In-Service Date: 9/30/2016 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):Northwestern Energy Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: NTTG
|
Navajo Transmission Project Segment #1 (Four Corners - Marketplace 500 kV) |
Project Purpose:Relieve current constraints west of Four Corners Area, improve reliability of EHV system in region, allow increased economical power sales and purchases, improve economic condition of Navajo Nation, facilitate development of Navajo Nation energy resources. Project Type: New Estimated In-Service Date: 1/1/2010 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):Dine Power Authority Voltage Class: WECC Project Rating Review Status: Phase 2 Subregional Planning Group:
|
North Gila - Imperial Valley #2 Project |
Project Purpose:Increase power transfer along WECC Path 46 as well as Path 49 Project Type: New Estimated In-Service Date: 1/1/2017 Estimated Transfer Capability/Rating (MW): 2,400 Sponsoring Organization(s):Southwest Transmission Partners, LLC Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: CTPG, SWAT
|
North Gila- TS8 230kV Line |
Project Purpose:This project serves the need for electric energy, improved reliability, and continuity of service for the greater Yuma area. This project is expected to be double circuit capable with one circuit in service in 2014 and the second circuit in service at a date to be determined. Project Type: New Estimated In-Service Date: 6/1/2014 Estimated Transfer Capability/Rating (MW): 188 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
NorthernLights |
Project Purpose:Purchase and sale of energy between Alberta and Pacific Northwest including up to 5,000 MW of wind and 3,500 MW of low emission cogeneration resources. Project Type: New Estimated In-Service Date: 1/1/2015 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):TransCanada Energy Voltage Class: >450kV DC WECC Project Rating Review Status: Phase 1 Subregional Planning Group:
|
Northwest Transmission Line |
Project Purpose:The project will provide a reliable supply of clean electricity to attract and support new industrial growth in the Northwest of British Columbia. Project Type: New Estimated In-Service Date: 12/31/2013 Estimated Transfer Capability/Rating (MW): 300 Sponsoring Organization(s):BC Hydro Voltage Class: <200kV AC, 200-300kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: BCCPG
|
NV Energy Self Build Robinson - Harry Allen 500 kV Line |
Project Purpose:This 500 kV line will interconnect transmission facilities in northern and southern Nevada, and facilitate the development of renewable energy generation in north, east and central Nevada. Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):NV Energy Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: SWAT, SIERRA
|
Palm Valley-TS2-Trilby Wash 230kV Line |
Project Purpose:This project will serve the need for electric energy in the western Phoenix Metropolitan area and additional import capability into the greater Phoenix Metropolitan area. The proposed second 230kV source for Trilby Wash provides improved system reliability and continuity of service for communities in the area; such as El Mirage, Surprise, Youngtown, Goodyear, and Buckeye. The first circuit is scheduled to be in-service for the summer of 2015;the in-service date for the second circuit will be evaluated in future planning studies. The in-service date for the TS2 substation is currently outside of the ten year planning horizon and will be continuously evaluated in future planning studies.
Project Type: New Estimated In-Service Date: 6/1/2015 Estimated Transfer Capability/Rating (MW): 1,200 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
Path 42 Upgrade Project |
Project Purpose:This project will enable WECC Path 42 (the sum of flows on Coachella Valley-Devers 230 kV and Mirage-Ramon 230 kV) to be able to transfer approximately 1,500 MW from Imperial Irrigation District (IID) to SCE's portion of the California Independent System Operator (CAISO) controlled grid and relieve congestion. Additionally, this project will contribute in meeting the RPS goal of 33% of retail load served by renewable resources by 2020.
Project Type: New Estimated In-Service Date: 12/31/2013 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):SCE Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group:
|
Path 8 Upgrade/Colstrip Transmission Upgrade |
Project Purpose:Provide capacity to relieve congestion on Path 8 and meet requests for transmission service to move renewable power from Montana to load centers outside Montana. Project Type: Upgrade Estimated In-Service Date: 12/31/2013 Estimated Transfer Capability/Rating (MW): 700 Sponsoring Organization(s):NorthWestern Energy (NWE), and some or all of the Colstrip Transmission System (CTS) (east of Townsend), Bonneville Power Administration (BPA) (west of Townsend) Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: NTTG
|
Pawnee-Daniels Park |
Project Purpose:This proposed project consists of approximately 124 miles of 345-kV transmission from Public Service Company of Colorado’s (PSCo) Pawnee Substation in northeastern Colorado to its Daniels Park Substation south of the Denver metro area.
The first 95 miles of the project would expand the planned Pawnee-Smoky Hill 345-kV transmission line so there is a double-circuit, 345-kV transmission line between Pawnee and Smoky Hill substations. One circuit would be the Pawnee-Smoky Hill 345-kV line, and the second circuit would be one section of the Pawnee-Daniels Park 345-kV line.
For the remaining 29 miles between PSCo’s Smoky Hill and Daniels Park substations, new double-circuit, 345-kV transmission line would be constructed. One of the two circuits would be the second portion of the Pawnee-Daniels Park 345-kV line. The second circuit would create a new 345-kV transmission line between PSCo’s Smoky Hill and Daniels Park substations.
This proposed project is expected to accommodate approximately 300-500 megawatts of resources, interconnecting at or near the Pawnee Substation. Project Type: New Estimated In-Service Date: 12/31/2018 Estimated Transfer Capability/Rating (MW): 1,733 Sponsoring Organization(s):Public Service of Colorado Voltage Class: 300-450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CCPG
|
Pawnee-Smoky Hill |
Project Purpose:This is a new, double-circuit capable, 345-kV transmission line to connect Public Service Company of Colorado’s (PSCo) existing Pawnee Substation near Brush, Colorado, to PSCo’s Smoky Hill Substation near Aurora, Colorado. The line will accommodate additional electric generation in northeast Colorado, particularly wind energy, and ensure reliable delivery of power to customers.
It will allow 300-500 megawatts of additional generation. It consists of three sections. The first section is approximately 79 miles of new 345-kV transmission extending from PSCo’s existing Pawnee Substation to a point east of PSCo’s existing Brick Center Substation, south of Bennett, Colorado. The second, or center section, consists of rebuilding approximately 15 miles of existing 230-kV wood pole structures to double-circuit, 345-kV-capable, steel-pole transmission. The third section is the last mile of transmission into the Smoky Hill Substation and consists of approximately one mile of new 345-kV transmission. This section also will be built to allow for double circuit, 345-kV capability.
PSCo filed the project Certificate of Public Convenience and Necessity (CPCN) in October 2007, which was approved by the Colorado Public Utilities Commission in February 2009. This project is in progress.
Project Type: New Estimated In-Service Date: 6/30/2013 Estimated Transfer Capability/Rating (MW): 1,733 Sponsoring Organization(s):Public Service of Colorado (PSCo) Voltage Class: 300-450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CCPG
|
Pinal Central – Sundance 230kV Line |
Project Purpose:This project will serve increasing loads in Pinal County, and throughout the APS system, and will improve reliability and continuity of service for the communities in the area. Also, the project will increase the reliability of Sundance by providing a transmission line in a separate corridor than the existing lines that exit the plant. Project Type: New Estimated In-Service Date: 6/1/2014 Estimated Transfer Capability/Rating (MW): 1,200 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
Pinal Central-Tortolita |
Project Purpose:The Pinal Central-Tortolita project is a single circuit 500 kV transmission line that will interconnect with the Pinal West-Pinal Central-Browning project (also known as Southeast Valley (SEV)). The project consists of 40 miles of new 500 kV transmission line between Pinal Central and Tortolita. The line will accommodate additional electric generation in central Arizona, including proposed new renewable energy, and ensure reliable delivery of power to customers in Southeast Arizona. It also will reinforce the statewide delivery system in support of meeting regional energy needs. Project Type: New Estimated In-Service Date: 4/15/2014 Estimated Transfer Capability/Rating (MW): 500 Sponsoring Organization(s):Tucson Electric Power Co. Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
Pinal West-Pinal Central-Browning (SEV) |
Project Purpose:The Pinal West-Pinal Central-Browning project (also known as Southeast Valley (SEV)) is under construction to strengthen the statewide delivery system in meeting regional energy needs. Project Type: New Estimated In-Service Date: 4/15/2014 Estimated Transfer Capability/Rating (MW): 1,400 Sponsoring Organization(s):Salt River Project Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
RTI Dixie-Oreana |
Project Purpose:To move renewable energy from NV Energy RTI zone 1 to Tracy 345 kV for export via GB HVDC or LMUD double-circuit 230 kV. Export is also possible to Eldorado if RTI West Side Tie is constructed. Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 800 Sponsoring Organization(s):NV Energy Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SIERRA
|
RTI Tracy-Viewland 345 kV |
Project Purpose:To move renewable energy from NV Energy RTI zone 2 north to Tracy 345 kV for export via GB HVDC or LMUD double-circuit 230 kV To move renewable energy from NV Energy RTI zone 1 north and west to Tracy 345 kV for export via GB HVDC or LMUD double-circuit 230 kV Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 800 Sponsoring Organization(s):NV Energy Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SIERRA
|
RTI Westside Tie 345 kV |
Project Purpose:To move renewable energy from NV Energy RTI zone 2 (Esmeralda Substation) north to Tracy 345 kV for export via GB HVDC or LMUD double-circuit 230 kV. To move renewable energy from RTI zone 2 south to to Amargosa 500 kV substaton and on to the Eldorado 500 kV substation via Northwest and Harry Allen Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 800 Sponsoring Organization(s):NV Energy Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SIERRA
|
RTI Zone 4 to Harry Allen |
Project Purpose:Move Solar Generation from Delamar valley and areas approximatley 40-60 Miles North of Las Vegas to Harry Allen and then to Eldorado Project Type: New Estimated In-Service Date: 12/12/2014 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):NV Energy Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SWAT
|
San Francisco Bay Area Bulk Transmission Reinforcement |
Project Purpose:Transmission reinforcements to reliably serve the load in the Greater Bay Area Project Type: New Estimated In-Service Date: 1/1/2013 Estimated Transfer Capability/Rating (MW): 0 Sponsoring Organization(s):Pacific Gas & Electric Voltage Class: WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
San Luis Rio Colorado (SLRC) Project |
Project Purpose:To interconnect a 600 MW gas fired, combined cycle power plant in San Luis Rio Colorado, state of Sonora, Mexico, with the Gila and N. Gila Substations. Project Type: New Estimated In-Service Date: 6/1/2014 Estimated Transfer Capability/Rating (MW): 1,600 Sponsoring Organization(s):North Branch Resources, Generadora del Desierto, SA de CV, and Western Area Power Administration Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: SWAT
|
San Luis Valley-Calumet-Comanche |
Project Purpose:Tri-State Generation and Transmission Association (Tri-State) and Public Service Company of Colorado (PSCo), an Xcel Energy company, are jointly proposing to construct, own and operate the San Luis Valley-Calumet-Comanche transmission project. It will enable efforts for the development of 600-1,000 megawatts of renewable energy and provide for better electric reliability on both Tri State’s and PSCo’s systems. The proposed project includes the following components:
■Approximately 95 miles of new, double-circuit 230-kilovolt (kV) transmission line from the existing San Luis Valley Substation, north of Alamosa, to a new Calumet Substation near Walsenburg.■A new 230/345-kV Calumet Substation on property currently owned by Tri-State located six miles north of Walsenburg and expansion of three existing substations.■Approximately 45 miles of new, double-circuit 345-kV transmission line between the proposed Calumet Substation and the existing Comanche Substation near Pueblo.■Approximately six miles of new 230-kV transmission line between the proposed Calumet Substation and the existing Walsenburg Substation.■Proposed communication facilities to support operation and maintenance of the transmission lines.PSCo submitted the project’s Certificate of Public Convenience (CPCN) and Necessity with the Colorado Public Utilities Commission in May 2009. The project is currently in the regulatory hearing process.
Project Type: New Estimated In-Service Date: 12/31/2016 Estimated Transfer Capability/Rating (MW): 1,400 Sponsoring Organization(s):Public Service of Colorado (PSCo) and Tri-State G&T Voltage Class: 200-300kV AC, 300-450kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group: CCPG
|
South Orange County Reliability Upgrade Project (SOCRUP) |
Project Purpose:Upgrade transmission facilities in SDG&E's Orange County service area, rebuild existing Capistrano substation and add 230kV. Project Type: Upgrade Estimated In-Service Date: 6/1/2017 Estimated Transfer Capability/Rating (MW): Sponsoring Organization(s):San Diego Gas & Electric Voltage Class: <200kV AC, 200-300kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CAISO
|
Southline Transmission Project (Afton-Apache) |
Project Purpose:The Southline Transmission Project is a proposed transmission line designed to collect and transmit electricity across southern Arizona and southern New Mexico to achieve three principal objectives:
1. Improve regional transmission grid reliability in southern New Mexico and southern Arizona;2. Mitigate existing congestion on the regional transmission grid; and3. Facilitate the interconnection of renewable energy resources Project Type: New Estimated In-Service Date: 12/31/2015 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Southline Transmission, L.L.C. Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: SWAT
|
Southline Transmission Project (Apache-Saguaro) |
Project Purpose:The Southline Transmission Project is a proposed transmission line designed to collect and transmit electricity across southern Arizona and southern New Mexico to achieve three principal objectives:
1. Improve regional transmission grid reliability in southern New Mexico and southern Arizona;2. Mitigate existing congestion on the regional transmission grid; and3. Facilitate the interconnection of renewable energy resources Project Type: Upgrade Estimated In-Service Date: 12/31/2015 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):Southline Transmission, L.L.C. Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: SWAT
|
Sun Valley – Trilby Wash 230kV Line |
Project Purpose:This project is required to serve the need for electric energy in the western Phoenix Metropolitan area. Also, the project will provide more capability to import power into the Phoenix Metropolitan area along with improved reliability and continuity of service for communities in the area including El Mirage, Surprise, Youngtown, Buckeye, and unincorporated Maricopa county. The first circuit is scheduled to be in-service for the summer of 2014 and the in-service date for the second circuit will be evaluated in future planning studies. Project Type: New Estimated In-Service Date: 6/1/2014 Estimated Transfer Capability/Rating (MW): 1,200 Sponsoring Organization(s):Arizona Public Service Company Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
Sunrise Powerlink |
Project Purpose:Access to renewable energy sources and increased system reliability. Project Type: New Estimated In-Service Date: 6/1/2012 Estimated Transfer Capability/Rating (MW): 1,000 Sponsoring Organization(s):San Diego Gas & Electric Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 Subregional Planning Group: CAISO
|
SunZia Southwest Transmission Project |
Project Purpose:Promote development of wind, solar and geothermal energy and increase reliability of the existing extra high voltage transmission systems in southern New Mexico and southern Arizona. Project Type: New Estimated In-Service Date: 1/1/2016 Estimated Transfer Capability/Rating (MW): 3,000 Sponsoring Organization(s):SouthWestern Power Group, Salt River Project, Tucson Electric Power, Shell WindEnergy, and Tri-State Generation & Transmission Association Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 3 completed Subregional Planning Group: SWAT
|
SWIP North |
Project Purpose:Improved system reliability, economic transfers between Northwest and Southwest, and delivery of wind resources (NV, ID, MT & WY) and geothermal resources (NV & UT). Project Type: New Estimated In-Service Date: 1/1/2014 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):Great Basin Transmission, LLC Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: SIERRA
|
SWIP South |
Project Purpose:Improved system reliability, economic transfers between Northwest and Southwest, and delivery of wind resources (NV, ID, MT & WY) and geothermal resources (NV & UT). Project Type: New Estimated In-Service Date: 1/1/2014 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):Great Basin Transmission, LLC Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: SIERRA, CAISO
|
TCP (Transmission Corridor Project, Amargosa-Northwest) |
Project Purpose:Interconnect renewable resources in Amargosa Valley with the NVE transmission system via Northwest Substation Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):NV Energy Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT, SIERRA
|
TCP (Transmission Corridor Project, Harry Allen - Eldorado) |
Project Purpose:Transfer Nevada Renewable Energy Resources to Eldorado Substation for export.
Note: Will Include installation of Harry Allen 500/230 kV Transformer Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):NV Energy Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT, SIERRA
|
TCP (Transmission Corridor Project, Northwest - Harry Allen) |
Project Purpose:Interconnect renewable resources in Amargosa Valley and near Harry Allen with the NVE transmission system Project Type: New Estimated In-Service Date: 12/12/2015 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):NV Energy Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT, SIERRA
|
TOT3 Archer Interconnection Project |
Project Purpose:Increased transfer capacity on the existing TOT3 (Path 36) Project Type: Upgrade Estimated In-Service Date: 12/31/2013 Estimated Transfer Capability/Rating (MW): 164 Sponsoring Organization(s):Tri-State G&T Voltage Class: WECC Project Rating Review Status: Phase 2 Subregional Planning Group:
|
TransWest Express Project |
Project Purpose:Delivery of cost effective wind energy to Arizona, California and Nevada Project Type: New Estimated In-Service Date: 1/1/2016 Estimated Transfer Capability/Rating (MW): 3,000 Sponsoring Organization(s):TransWest Express, LLC Voltage Class: >450kV DC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: CTPG, NTTG, SWAT
|
Tres Amigas |
Project Purpose:Interconnect Eastern, Western and ERCOT grids. Project Type: New Estimated In-Service Date: 10/1/2014 Estimated Transfer Capability/Rating (MW): 750 Sponsoring Organization(s):Tres Amigas, LLC Voltage Class: 300-450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT
|
Triton HVDC Sea Cable Project |
Project Purpose:TBD Project Type: New Estimated In-Service Date: 1/1/2013 Estimated Transfer Capability/Rating (MW): 1,600 Sponsoring Organization(s):Sea Breeze Pacific Regional Transmission System, Inc (SBP-RTS) Voltage Class: WECC Project Rating Review Status: Phase 0 Subregional Planning Group:
|
Walla Walla to McNary 230 kV (Energy Gateway Segment A) |
Project Purpose:To meet transmission srvice request agreements; support new renewable energy development Project Type: New Estimated In-Service Date: 12/31/2013 Estimated Transfer Capability/Rating (MW): 400 Sponsoring Organization(s):PacifiCorp Voltage Class: 200-300kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: NTTG
|
WECC - Eastern Interconnect DC Tie Upgrade Project |
Project Purpose:Increase the existing AC-DC-AC ties in increments of 100MW, for a total of approximately 600MW Project Type: Upgrade Estimated In-Service Date: 5/1/2015 Estimated Transfer Capability/Rating (MW): 100 Sponsoring Organization(s):Energy Capital Partners
PDS Consulting Voltage Class: 200-300kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: CCPG, SWAT
|
West Coast Cable Project |
Project Purpose:Provide the California market access to hydroelectric energy and untapped wind resources in the Pacific Northwest Project Type: New Estimated In-Service Date: 1/1/2016 Estimated Transfer Capability/Rating (MW): 1,500 Sponsoring Organization(s):Sea Breeze Pacific West Coast Cable, LP Voltage Class: WECC Project Rating Review Status: Phase 1 Subregional Planning Group:
|
West of McNary Reinforcement Project Group 1 (McNary - John Day) |
Project Purpose:Capacity increase and congestion relief to serve point to point transmission service requests which impact the West of McNary (WOM) / West of Slatt (WOS)/West of John Day (WOJ) flowgates.
Project Type: New Estimated In-Service Date: 2/28/2012 Estimated Transfer Capability/Rating (MW): Sponsoring Organization(s):Bonneville Power Administration Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: CG
|
West of McNary Reinforcement Project Group 2 (Big Eddy - Knight) |
Project Purpose:Capacity increase and congestion relief to serve point to point transmission service requests which impact the West of McNary (WOM) / West of Slatt (WOS)/West of John Day (WOJ) flowgates. Project Type: New Estimated In-Service Date: 2/28/2013 Estimated Transfer Capability/Rating (MW): Sponsoring Organization(s):Bonneville Power Administration Voltage Class: >450kV AC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: CG
|
West Side Tie |
Project Purpose:Interconnect renewable resources in the Northern Nevada with the NVE transmission system and deliver them to the load centers in the South. Project Type: New Estimated In-Service Date: 12/12/2018 Estimated Transfer Capability/Rating (MW): 2,000 Sponsoring Organization(s):NV Energy Voltage Class: >450kV AC WECC Project Rating Review Status: The project has not entered the WECC Path Rating process Subregional Planning Group: SWAT, SIERRA
|
Wyoming-Colorado Intertie Project |
Project Purpose:To increase TOT3 capacity and facilitate new Wyoming generation resources pursuant to transmission service requests Project Type: New Estimated In-Service Date: 1/1/2016 Estimated Transfer Capability/Rating (MW): 900 Sponsoring Organization(s):Wyoming-Colorado Intertie, llc(member of LS Power Group) and Wyoming Infrastructure Authority Voltage Class: 300-450kV AC WECC Project Rating Review Status: Phase 2 Subregional Planning Group: CCPG
|
Zephyr |
Project Purpose:Facilitate movement of renewable energy from Wyoming to California and the Desert Southwest Project Type: New Estimated In-Service Date: 12/31/2020 Estimated Transfer Capability/Rating (MW): 3,000 Sponsoring Organization(s):DATC (Duke-American Transmission Co.) Voltage Class: >450kV DC WECC Project Rating Review Status: Phase 1 Subregional Planning Group: CTPG, NTTG, SWAT, CAISO
|